|
COPYRIGHT NOTICE
Reproduction of any material from this website
(text or photographic) is strictly forbidden without the prior permission of the
copyright owner.
If you would like to use any of the material on
this website, please contact me via the Feedback page, and I will put you in
contact with the appropriate copyright owner.
Every effort is made to ensure that photographs
on this website are produced with the consent of the copyright owner. If you
believe any image on this website to be in breach of copyright, please contact
me immediately so that it can be removed.
| |
|
PRESTON
STATION REMODELLING |
Preston
Station Remodelling
BY MIKE NORRIS
Mike would like to
hear from anyone involved with the remodelling and resignalling of
the station and surrounding area to aid historical research for
future documentation, please contact via the Feedback
page.
|
SECTION
CONTENTS
1. Background
2. Project
Approval & Planning
3. The
Work at Preston
4. Signalling
& Power Box Commissioning
5. Electrification,
Catenary & Electricity Supply
6. Delays
7. Locomotives
8. Media
9. It's
Official! |
| 4.
Signalling & Power Box Commisssioning |
| Signalling |
| These track and
signalling rationalizations paved the way for the power box
commissioning.
Since 1939 Preston had been in need of renewal, the mechanical
signalling soldiering on for another 30 years due to piece-meal, like
for like, replacement and associated high maintenance costs.
With the introduction of this new power box at Preston manpower
savings were expected of 194 signalmen’s positions on the
West Coast main line and 147 with the following phase covering
the East Lancashire main line.
The signalling contracts worth over £13m were awarded to
AEI-General Signal Limited and Westinghouse Brake & Signal Co.
Ltd. By the Scottish and London Midland regions, for complete
re-signalling of the West Coast main line.
The Westinghouse contract covered three signal boxes Warrington (50
route miles), Preston (114 route miles) and Carlisle (104 route miles)
replacing no less than 178 manual signal boxes. In addition to the
main signalling contract for £7.5m, Westinghouse secured an order
worth £629,000 for a computer based train describer system.
Warrington was the first to be commissioned in September/October
1972. The Preston box was commissioned in several phases usually
performed over a weekend starting with the link up from Warrington.
|
Here
we can see the new goods line and platform six taking shape, the line
in the foreground were the former platforms eight and nine. Currently
these are stopped off to provide bay platforms. The East Lancs side of
the station is now out of use for service trains but is retained for
the engineers trains. Preston No.3 signal box can be seen in the
centre of the picture which closed on the 13th March 1972. There is a
new temporary semaphore just to left of the signal box which will be
worked by Preston No.1 until the PSB takes over in February 1973. |
| Power Box
Commissioning |
| The power box was
commissioned as a series of phases as already mentioned; more details
and dates on this can be found in the section Preston
Signalling by David Ingham.
During the Stage 1 commissioning work Farington Junction box would
act as the link up box from October until November 1972, with the area
south under the control of the new power box, while the tracks north
would remain under mechanical control.
Stage 2 would take the south link north to Skew Bridge, until the
final Stage 7 work (February 1973).
The most northerly work was stage 6 carried out in January 1973.
Carnforth No.2 and Burton and Holme would remain in use until Stages 7
and 8 of Carlisle scheme were implemented over the weekend of the 12th
and 13th May 1973. This would mark the conclusion of the
route to Carlisle.
The Stage 7 work was the Preston station area and linked the
northern (Oxheys) and southern areas, which had already been
commissioned, together. It took in the Fylde lines, with Salwick No.2
becoming the fringe box.
This only left East Lancashire to be completed.
Strand road box became a ground frame and the Deepdale branch at
the former Preston No.5 end, now came under the control of the power
signal box.
Between Weaver Junction and Gretna a total of 811 signals were
required, along with 562 miles of telecoms cable.
The sheer scale of the re-signalling project at Preston really has
to be admired, it was the largest installation of the three power
boxes, here are a few statistics:
Manual signal boxes abolished 87
Fringe boxes and token stations 11
Colour light signals 466 (254 Warrington 325 Carlisle)
Routes signalled 866 (232 Warrington, 553 Carlisle)
Point Machines 364
Track Circuits 1050
Route miles 114
Track miles 263 (145 Warrington 221 Carlisle)
|
|
|
| |
|